


Contents
1.4 Construction
Works Undertaken During the Reporting Month
1.5 Schedule
and Progress of EP Submission
2.2 Monitoring
Schedule and Summary of Impact Air Quality Monitoring Results
3.2 Monitoring
Schedule and Summary of Impact Construction Noise Monitoring Results
4.2 Summary
of Monitoring Results
5 Environmental
Site Inspection and Audit
5.1 Environmental
Site Inspection
6 Report on
the Non-compliances, Complaints, Notifications of Summons and Status of
Prosecutions
6.1 Summary
of Exceedance of the Environmental Quality Performance Limit
6.2 Summary
of Complaints, Notifications of Summons and Successful Prosecutions
6.3 Implementation
Status of Environmental Protection and Pollution Control / Mitigation Measures
7.1 Construction
Programme for the Upcoming Month
7.2 Environmental
Site Inspection and Monitoring Schedule for the Next Reporting Period
8 Conclusions
and Recommendations
Table 1.1: Contact Information of Key Personnel
Table 1.2: Status of the Submissions as Required under
the EP
Table 2.1: Impact Air Quality Monitoring Stations
Table 2.2: Equipment Used During the Impact Air Quality
Monitoring in the Reporting Period
Table 2.3: Action and Limit Levels for Air Quality
Table 2.4: Summary of Impact Air Quality Monitoring
Results
Table 3.1: Noise Monitoring Stations
Table 3.2: Equipment Used During the Impact Construction
Noise Monitoring in the Reporting Period
Table 3.3: Action and Limit Levels for Construction Noise
Table 3.4: Summary of Impact Noise Monitoring Results
Table 4.1: Water Quality Monitoring Stations
Table 4.2: Action and Limit Levels for Water Quality
Table 4.3: Corresponding Control and Impact Monitoring
Stations during Impact Monitoring
Table 5.1: Summary of Site Inspections and
Recommendations
Table 5.2: Valid Environmental Permits / Licences
Table 6.1: Statistics on Exceedance of the Action or
Limit Levels for Environmental Monitoring
Figures
Figure 1.1: Location of the Project
Figure 1.2: Construction Activities
Undertaken during the Reporting Period
Figure 2.1: Air Quality Monitoring
Stations
Figure 3.1: Noise Monitoring Stations
Figure 4.1: Water Quality Monitoring
Stations
Appendices
B. Construction Works Programme
C. Environmental Monitoring Results
F. Environmental Monitoring and
Site Inspection Schedule
H. Implementation Schedule of
Environmental Mitigation Measures
Executive
Summary
The construction works of the Airport Tung Chung Link (“ATCL”) Project commenced
on 17 December 2025; therefore, the construction phase EM&A programme of
the ATCL Project started on 17 December 2025. This is the 2nd
Monthly EM&A report summarising the key findings of the construction phase
EM&A programme from 1 to 31 January 2026 (the reporting period) and is
submitted to fulfil requirements in Condition 3.4 of EP and Section 12.3 of
EM&A Manual of the Project.
During the reporting period, no marine works in
relation to the marine viaduct was undertaken thus no water quality monitoring
was conducted. The ET of the ATCL Project has undertaken environmental site
inspections and environmental monitoring under the construction phase EM&A
programme during the reporting period.
Table I: Summary of Monitoring
Activities in the Reporting Period
|
Monitoring Activities |
Date of Monitoring Events |
Number of Monitoring Events |
|
Air Quality Monitoring |
3, 9, 15, 21 and 27 Jan 2026 |
5 |
|
Noise Monitoring |
6, 12, 23 and 29 Jan 2026 |
4 |
Breaches
of Action and Limit Levels
Air quality and noise monitoring was conducted
during the reporting period, and no exceedance was recorded.
Site
Inspection
During the reporting period, four (4) site
inspections were carried out on 5, 12, 23 and 27 January 2026, joint IEC site
inspection with Environmental Management Meeting was carried out on 23 January
2026.
Complaint
Log
There was no complaint received in relation to
the environmental impact during the reporting period.
Notifications
of Summons and Successful Prosecutions
There was no notification of summons or
successful prosecutions received during the reporting period.
Reporting
Changes
There was no reporting change during the
reporting period.
Key
Activities in the Reporting Period
As informed by the Contractor, the major
construction activities for the reporting period are summarised below:
Land-based
portion
·
Pre-drilling
(site preparation works); and
·
Tree
felling (site preparation works).
Marine-based
portion
·
Pre-drilling
(site preparation works).
Future Key
Issues
As informed by the Contractor, the major
construction activities for the next reporting period are summarised below:
Land-based
portion
·
Pre-drilling
(site preparation works);
·
Site
clearance (site preparation works); and
·
Piling
works.
Marine-based
portion
·
Pre-drilling
(site preparation works).
The project proponent, Airport
Authority Hong Kong (“AAHK”) is planning to construct a dedicated road, named
as the Airport Tung Chung Link (“ATCL”), to extend the passenger transport
services using autonomous vehicles (“AV”) from the Airportcity Link (“ACL”),
which is currently under construction, to Tung Chung, aiming to enhance
connectivity between the Hong Kong Port (“HKP”), SKYCITY and Tung Chung.
ATCL Project (hereafter referred to
as “the Project”), comprising ATCL and the marine facilities in the waters
between Airport Island and HKP Island, is a designated project under
Environmental Impact Assessment Ordinance (“EIAO”). The ATCL Project
Environmental Impact Assessment Report (“EIAR”) (Register No. AEIAR-254/2023)
was approved by the Director of Environmental Protection (“DEP”) and an
Environmental Permit No. EP-630/2023 for the construction and operation of the
ATCL Project was first granted by DEP to AAHK on 26 October 2023. Subsequently
an application for variation of the Environmental Permit was submitted on 3
November 2025 and the current valid Environmental Permit (No. EP-630/2023/A)
(hereafter referred to as “the EP”) was issued by Environmental Protection
Department (“EPD”) on 1 December 2025.
The marine facilities in the waters between
Airport Island and HKP Island are included in the ATCL
Project EIAR (Register No. AEIAR-254/2023) and the ATCL Project EP (EP No.
EP-630/2023/A), however, the construction of marine facilities and spur
line of ATCL (including Academy Station) are not included in the current stage
of ATCL construction. The
alignment of ATCL is shown in Figure
1.1.
In February 2025, Mott MacDonald Hong Kong
Limited (MMHK) was commissioned by AAHK under Contract C24C02 to provide
Environmental Team (ET) consultancy services for implementation of an EM&A
programme in accordance with the ATCL Project EP
requirements throughout the Pre-construction, Construction and
Post-construction phases of the ATCL Project. The construction phase EM&A
programme of the ATCL Project started on 17 December 2025.
This is the 2nd Monthly EM&A
report summarising the key findings of the construction phase EM&A
programme from 1 to 31 January 2026 (the reporting period) and is submitted to
fulfil requirements in Condition 3.4 of EP and Section 12.3 of EM&A Manual
of the Project.
The organisation chart and lines of
communication with respect to the on-site environmental management structure of
the key personnel are shown in Appendix
A. The key personnel contact names and numbers are summarized in Table 1.1.
Table 1.1: Contact Information of Key
Personnel
|
Party |
Position |
Name |
Telephone |
|
Project Manager’s Representative (Airport Authority Hong Kong) |
Principal Manager, Environmental Compliance, Sustainability |
Lawrence Tsui |
2183 2734 |
|
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Thomas Chan |
2828 5967 |
|
Deputy Environmental Team Leader |
Ken Wong |
2828 5817 |
|
|
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Lemon Lam |
3856 5680 |
|
Main Contractor of Contract No. C24W08 (Penta-Ocean Construction Co. Ltd.) |
Project Manager |
Hiroshi Fujimoto |
9165 4070 |
|
Environmental Manager |
Gideon Cheng |
9731 5852 |
|
|
Senior Environmental Officer |
So Chi Ho |
9139 3831 |
The construction phase EM&A programme of
the Project started on 17 December 2025. During the reporting period, no marine
works in relation to the marine viaduct was undertaken.
The construction works programme and the
construction works area of the Project are shown in Appendix B and Figure 1.1 respectively.
A summary of construction activities undertaken
during this reporting period is presented in Figure 1.2 and summarised below:
Land-based
portion
·
Pre-drilling
(site preparation works); and
·
Tree
felling (site preparation works).
Marine-based
portion
·
Pre-drilling
(site preparation works).
The status of the submissions as required in
the EP is presented in Table 1.2.
Table 1.2: Status of the Submissions as Required
under the EP
|
EP Condition |
Submission |
Submission Timeframe |
Status |
|
2.8 |
EP Submission Schedule |
No later than 1 month before the commencement of construction of the Project |
Submitted and accepted by the EPD |
|
2.9 |
Management Organization |
No later than 2 weeks before the commencement of construction of the Project |
Submitted and accepted by the EPD |
|
2.10 |
Construction Works Schedule and Location Plans |
No later than 2 months before the commencement of construction of the Project |
Submitted and accepted by the EPD |
|
2.11 |
Construction Noise Management Plan |
No later than 2 months before the commencement of construction works of the Project |
Submitted and accepted by the EPD |
|
2.13 |
Silt Curtain Deployment Plan |
No later than 2 months before the commencement of marine works involving deployment of silt curtains of the Project |
Submitted |
|
2.14 |
Landscape and Visual Mitigation Plan |
No later than 2 months before the commencement of construction of the Project or otherwise approved by the Director |
Submitted |
|
2.17 |
Noise Performance Test Report for Zero Emission Vehicles |
At least 2 months before commencement of operation of the Project |
-- |
|
3.3 |
Baseline Monitoring Report |
At least 2 weeks before the commencement of construction of the Project |
Submitted and accepted by the EPD |
According to the Sections 3.2.23 to
3.2.28 in the ATCL Project EM&A Manual, impact air quality monitoring for
1-hour Total Suspended Particulates (TSP) should be carried out at designated
monitoring locations for at least three times in every six days when the
highest dust impacts occur. Further details of the impact air quality
monitoring are presented in the following sections.
1-hour TSP levels have been measured during
impact air quality monitoring in accordance with the ATCL Project EM&A
Manual. The monitoring information (e.g. monitoring date, monitoring time,
weather conditions, dust source(s), other specific phenomena) was recorded in
the data record sheet during the monitoring.
The monitoring locations for impact
air quality monitoring are summarised in Table 2.1 and shown in Figure 2.1.
Table 2.1: Impact Air Quality Monitoring Stations
|
ID |
ASR ID adopted in EIA Report |
Description |
Monitoring Parameter |
Monitoring Level |
|
AM1a (1) |
--- |
Tat Tung Road Garden |
1-hour TSP |
Ground Floor |
|
AM2 |
A11 |
Hong Kong Airlines Training Academy |
1-hour TSP |
Ground Floor |
|
AM3 |
A10 |
CNAC House |
1-hour TSP |
Podium |
Remark:
(1) As advised by the Leisure and Cultural Services
Department, Tung Chung Community Garden (original monitoring station ID: AM1;
ASR ID: A20) as stipulated in Table 3.1 of the ATCL Project EM&A Manual has
been decommissioned and hence not accessible. Therefore, Tat Tung Road Garden
which located next to the Tung Chung Community Garden is proposed to be the
alternative air quality monitoring station. The proposed alternative location
was agreed by the Independent Environmental Checker (“IEC”) and AAHK on 3 April
2025 and approved by EPD on 2 June 2025.
Impact air quality monitoring station, AM4, which is designated in the
ATCL Project EM&A Manual for the proposed marine facilities during
construction phase is not included in this report, as the construction of
marine facilities is not part of the current stage of ATCL construction (refer
to Section 1.1).
Direct reading method by the use of portable
direct reading dust meters was proposed to be used for impact air quality
monitoring for this ATCL Project, based on the provisions set out in Section
3.2.7 of the ATCL Project EM&A Manual. With the use of portable direct
reading dust meters, it can allow prompt and direct results for the EM&A
reporting and the implementation of the Event and Action Plan. The proposal for
adopting direct reading method by the use of portable direct reading dust
meters was approved by the IEC.
General meteorological conditions throughout
the impact monitoring period were recorded. It is considered that the wind data
obtained at the existing Hong Kong Observatory’s (HKO) Chek Lap Kok wind
station is representative of the Project area and could be used for undertaking
the impact air quality monitoring programme for the ATCL Project. The proposed
use of the existing wind data collected from Chek Lap Kok wind station for wind
data collection instead of setting up wind monitoring equipment near the
monitoring stations was proposed by the ET Leader and agreed by the IEC, in
accordance with the requirements stated in Section 3.2.9 of the ATCL Project
EM&A Manual.
The measuring procedures of the portable direct
reading dust meter are followed in accordance with the Manufacturer’s
Instruction Manual as presented below:
SIBATA
model no. LD-3B
a) set POWER to “ON” and make sure that the
battery level was not flash or in low level;
b) pull the air sampling inlet cover up;
c) push the knob at [MEASURE] position;
d) set time/mode setting to [BG] by pushing the
time setting switch;
e) start the background measurement by pushing the
Start/Stop switch once;
f) turn knob to [SENSI. ADJ] position
and push Start/Stop switch once to start the span check;
g) gently return knob to the [MEASURE] position;
h) push the time setting switch to change the time
setting display to [LOG];
i) remove the cap and start
measurement.
SIBATA
model no. LD-5R
a) turn ON the power switch;
b) close the air sampling port cap;
c) turn the scattering plate knob to [MEASURE];
d) perform the BG measurement (8 seconds + 6
seconds);
e) turn the scattering plate knob to [SENSI.
ADJ.];
f) perform the SPAN measurement (60
seconds);
g) turn the scattering plate knob to [MEASURE];
h) open the air sampling port cap;
i) select the measurement mode;
j) start the measurement;
k) finish the measurement (automatically or
manually);
l) close the air sampling port cap;
m) perform the BG measurement (8 seconds + 6 seconds);
n) turn OFF the power switch
Table 2.2 summarises the equipment used in
the reporting period. Copies of the calibration certificates for the equipment
used during the reporting period are attached in Appendix D. The portable direct
reading dust meter would be calibrated every year against High Volume Sampler
(HVS) to check the validity and accuracy of the results measured by direct
reading method.
Table 2.2: Equipment Used During the Impact Air
Quality Monitoring in the Reporting Period
|
Equipment |
Model |
|
Portable Direct Reading Dust Meter
|
SIBATA LD-3B (serial no. 456668) |
|
SIBATA LD-3B (serial no. 6z7784) |
In accordance with the ATCL Project EM&A
Manual, baseline air quality monitoring of 1-hour TSP levels at the air quality
monitoring stations were established as presented in the Baseline Monitoring
Report. The Action and Limit Levels of the impact air quality monitoring are
presented in Table 2.3.
Table 2.3: Action and Limit Levels for Air Quality
|
Parameter |
Monitoring Station |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|
1-hour TSP Level in μg/m3 |
AM1a |
270 |
500 |
|
AM2 |
274 |
500 |
|
|
AM3 |
275 |
500 |
Should
non-compliance of the air quality criteria occur, actions in accordance with
the Event and Action Plan in Appendix
E shall be carried out.
Impact air quality monitoring was conducted on
3, 9, 15, 21 and 27 January 2026 during the reporting period. The schedule of
impact air quality monitoring conducted in the reporting period is provided in Appendix F. The impact air quality
monitoring results obtained in the reporting period are summarised in Table 2.4, with detailed impact air quality monitoring
results, graphical presentation and wind data presented in Appendix C.
Table 2.4: Summary of Impact Air Quality Monitoring
Results
|
Monitoring Station |
1-hr TSP Concentration Range (μg/m3) |
Average 1-hr TSP Concentration (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|
AM1a |
28 - 49 |
40 |
270 |
500 |
|
AM2 |
26 - 63 |
44 |
274 |
500 |
|
AM3 |
23 - 57 |
42 |
275 |
500 |
During the monitoring, no specific observation
was noted in the vicinity.
The monitoring results were within the
corresponding Action and Limit Levels at all monitoring stations in the
reporting period and no exceedance for impact air quality monitoring was
recorded.
According to the Section 4.3.11 in
the ATCL Project EM&A Manual, impact construction noise monitoring for Leq
(30min) should be carried out at designated monitoring locations once
every week when there are project-related construction activities being
undertaken within a radius of 300m from the monitoring stations. Further
details of the impact construction noise monitoring are presented in the
following sections.
Construction noise level should be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30min) shall be used as the monitoring parameter for the time
period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5min) shall be employed for comparison with the Noise
Control Ordinance (NCO) criteria. As supplementary information for data
auditing, statistical results such as L10 and L90 were
also obtained for reference.
The monitoring locations for impact
construction noise monitoring are summarised in Table 3.1
and shown in Figure 3.1.
Table 3.1: Noise Monitoring Stations
|
Monitoring Station ID |
Representative NSR ID in EIA Report |
Description |
Monitoring Level |
Type of Measurement |
|
NM1 |
N01 |
Seaview Crescent |
Roof-top of Block 1 (Direction: SW) |
Facade measurement |
|
NM2 |
N03 |
Ling Liang Church E Wun Secondary School |
Roof-top (Direction: W) |
Facade measurement |
|
NM3 |
N08 |
Fu Tung Estate Tung Ma House |
Roof-top (Direction: N) |
Facade measurement |
|
NM4 |
N09 |
Tung Chung Crescent |
Roof-top of Block 5 (Direction: NE) |
Facade measurement |
|
NM5(1) |
N10 |
Priests’ Quarters of the Planned Visitation Church Development |
-- |
--
|
Remark:
(1) The Priests’ Quarters of the Planned Visitation
Church Development is under construction during the impact noise monitoring
period. Subject to the construction programme of the planned NSR, its impact
monitoring status will be reviewed when necessary.
Hand-held sound level meter was used for impact
noise monitoring. Sound level meter in compliance with the International
Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type
1) specifications was used for carrying out the impact construction noise
monitoring. Immediately prior to and following each noise measurement, the
accuracy of the sound level meter was checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. The noise
measurements were made in accordance with standard acoustical principles and
practices in relation to weather conditions. Measurements would be accepted as
valid only if the calibration level from before and after the noise measurement
agrees to within 1.0 dB.
Table 3.2 summarises the equipment used in
the reporting period. Copies of the calibration certificates for the equipment
used during the reporting period are attached in Appendix D.
Table 3.2: Equipment Used During the Impact
Construction Noise Monitoring in the Reporting Period
|
Equipment |
Model |
|
Sound Level Meter |
Rion NL-53 (serial no. 01141565) |
|
Acoustic Calibrator |
CAL 200 (serial no.: 10227) |
The Action
and Limit Levels of the impact noise monitoring are presented in Table 3.3.
Table 3.3: Action and Limit Levels for Construction
Noise
|
Time Period |
Action Level |
Limit Level (Leq (30min), dB(A)) |
|
|
NM1 |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75 |
|
NM2 |
70 dB(A) and 65 dB(A) during examination period |
||
|
NM3 |
75 |
||
|
NM4 |
75 |
||
|
NM5 |
75 |
Should non-compliance of the construction noise
criteria occur, actions in accordance with the Event and Action Plan in Appendix E shall be carried out.
Impact construction noise monitoring was
conducted on 6, 12, 23 and 29 January 2026 during the reporting period. The
schedule of impact construction noise monitoring conducted in the reporting
period is provided in Appendix F.
The impact noise monitoring results obtained in the reporting period are
summarised in Table 3.4, with detailed impact noise
monitoring results and graphical presentation presented in Appendix C.
Table 3.4: Summary of Impact Noise Monitoring
Results
|
Monitoring Station |
Noise Level Range (Leq (30min), dB(A)) |
Limit Level (Leq (30min), dB(A)) |
|
NM1 (2) |
54 - 65 |
75 |
|
NM2 (2) |
57 - 64 |
65 / 70(1) |
|
NM3 |
64 - 65 |
75 |
|
NM4 |
63 - 64 |
75 |
Notes:
(1) Will be reduced to 65dB(A) during school
examination periods. School examination took place from 5 to 21 January 2026
during this reporting period.
(2) When the noise measurement results being higher
than the baseline monitoring levels, to reduce the influence of non-Project
related noise on the monitoring results, those measurement results would be
corrected with reference to the baseline monitoring results.
During the monitoring, traffic noise was noted
in the vicinity.
No complaint was received from any sensitive
receiver that triggered the Action Level. All monitoring results were also
within the corresponding Limit Levels at all monitoring stations in the
reporting period. Therefore, no exceedance for impact construction noise
monitoring was recorded during the reporting period.
According to the Sections 5.7.7 to
5.7.11 in the ATCL Project EM&A Manual, impact water quality monitoring
should be carried out at designated monitoring locations for three days per
week, at mid-flood and mid-ebb tides. Further details of the impact water
quality monitoring are presented in the following sections.
Monitoring for Dissolved Oxygen
(DO), Dissolved Oxygen Saturation (DO%), temperature, pH, turbidity, salinity,
suspended solid (SS) and water depth should be undertaken at all designated
monitoring locations. All parameters should be measured in-situ
whereas SS should be determined by an accredited laboratory. DO should be
presented in mg/L and in % saturation.
Two replicate in-situ
measurements and samples collected from each independent sampling event shall
be collected to ensure a robust statistically interpretable database.
Other relevant data should also be
recorded, including monitoring location / position, time, water depth, tidal
stages, weather conditions and any special phenomena or work underway at the
construction site.
The marine facilities in the waters between
Airport Island and HKP Island are included in the approved ATCL Project EIAR
and the ATCL Project EP, however, the construction of marine facilities is not
included in the current stage of ATCL construction. Therefore, water quality
monitoring will only be undertaken for the marine water quality monitoring
stations for the marine viaduct (namely IM2, IM3, SR3, C3 and C4).
The monitoring locations for impact water
quality monitoring are summarised in Table 4.1 and
shown in Figure 4.1.
Table 4.1: Water Quality Monitoring Stations
|
Stations |
Descriptions |
Easting |
Northing |
|
IM2 |
Impact Station |
812258 |
817871 |
|
IM3 |
Impact Station |
810725 |
816626 |
|
SR3 |
Seawater Intake at Tung Chung |
811780 |
817172 |
|
C3 |
Control Station |
812785 |
818754 |
|
C4 |
Control Station |
809533 |
817234 |
Measurement should be taken at 3 water depths,
namely, 1m below water surface, mid-depth and 1m above sea bed, except where
the water depth less that 6m, the mid-depth station may be omitted.
Should the water depth be less than 3m, only the mid-depth station will be
monitored.
Duplicate in-situ measurements and water
samples collected from each independent monitoring event are required for all
parameters to ensure a robust statistically interpretable dataset. At each
measurement depth, two consecutive measurements would be taken. The
probes would be retrieved out of the water after the first measurement and then
redeployed for the second measurement. When the difference in value
between the first and second measurement of on-site parameters is more than 25%
of the value of the first reading, the reading shall be discarded and further
readings shall be taken.
In addition, no sampling should be carried out
when typhoon signal No. 3 or above or black rainstorm signal is hoisted.
Monitoring
Equipment
In-situ measurements at monitoring locations including
dissolved oxygen (DO), dissolved oxygen saturation (DO%), pH, temperature,
turbidity, salinity and water depth shall be collected.
Calibration
of in-situ instruments
In-situ monitoring instruments for water quality
parameters shall be checked, calibrated and certified by a laboratory
accredited under HOKLAS before use. Responses of sensors and electrodes shall
be checked with certified standard solutions before each use.
Calibration certificates of the monitoring
equipment used in the reporting period will be supplemented once impact water
quality monitoring commences.
Sample
Containers and Storage
Water samples for SS determination shall be
stored in high density polythene containers with no preservative added, packed
in ice (cooled to 4oC without being frozen) and delivered to the
testing laboratory within 24 hours of collection and analysed as soon as
possible after collection.
In accordance with the ATCL Project EM&A
Manual, baseline water quality monitoring at the water quality monitoring
stations were established as presented in the Baseline Monitoring Report. The
Action and Limit Levels of the impact water quality monitoring are presented in
Table 4.2.
Table 4.2: Action and Limit Levels for Water Quality
|
Parameters |
Action Level |
Limit Level |
|
DO in mg/L |
Surface and Middle 5.1 Bottom 3.5 |
Surface and Middle 4.0 Bottom 2.0 |
|
SS in mg/L |
Depth Average 10.8 and 120% of upstream control station at the same tide of the same day |
Depth Average 13.4 and 130% of upstream control station at the same tide of the same day |
|
Turbidity in NTU |
Depth Average 7.9 and 120% of upstream control station at the same tide of the same day |
Depth Average 9.9 and 130% of upstream control station at the same tide of the same day |
Notes:
1. "Depth Average" is calculated by
taking the arithmetic means of reading of all sampling depths.
2. For DO, non-compliance of the water quality
limits occurs when monitoring result is lower than the limits.
3. For turbidity and SS, non-compliance of the
water quality limits occurs when monitoring result is higher than the limits.
4. All the figures given in the table are used for
reference only and the EPD may amend the figures whenever it is considered as
necessary.
As learnt from the dominant flow direction,
control station C4 will be at the upstream during ebb tide while control
station C3 will be at the upstream during flood tide. As such, control station
C4 will act as the control station during the ebb tide while control station C3
will act as the control station during the flood tide. The arrangement during
the impact monitoring is detailed in Table 4.3.
Table
4.3: Corresponding Control and Impact Monitoring Stations during Impact
Monitoring
|
Tidal Direction |
Control Station |
Impact Stations |
|
Ebb Tide |
C4 |
IM2, IM3, SR3 |
|
Flood Tide |
C3 |
IM2, IM3, SR3 |
Should non-compliance of the water quality
criteria occur, actions in accordance with the Event and Action Plan in Appendix E shall be carried out.
During the reporting period, no marine works in
relation to the marine viaduct was undertaken; therefore, no impact water
quality monitoring was conducted in the reporting period.
Site inspections were carried out by ET on a
weekly basis to monitor the implementation of proper environmental pollution
control mitigation measures for the Project. Key observations were recorded in
the site inspection checklist and passed to the Contractor together with the
appropriate recommended mitigation measures where necessary.
During the reporting period, weekly site
inspections were carried out on 5, 12, 23 and 27 January 2026. Joint IEC site
inspection was carried out on 23 January 2026. Bi-weekly landscape and visual
site audit was carried out on 12 and 27 January 2026. The site inspection
schedule is provided in Appendix F.
Key
observations and reminders during the site inspections and landscape and visual
site audit are described in Table 5.1.
Table 5.1: Summary of Site Inspections and
Recommendations
|
Inspection Date |
Key Observations / Reminders |
Recommendations / Actions |
Close-Out Date |
|
29 Dec 2025 |
At Viaduct 1 & 3, the NRMM labels of drill rigs were faded and damaged. |
NRMM labels were replaced on the drill rigs. |
5 Jan 2026 |
|
29 Dec 2025 |
At Viaduct 1, the generator and oil container were found without spillage prevention measures. |
Chemical container removed from surface. Temporary spillage prevention measure was applied to the generator. |
5 Jan 2026 |
|
29 Dec 2025 |
At Viaduct 1, a hand-held breaker was found on site without a valid Noise Emission Label (NEL). |
Handheld breaker without Noise Emission Label was removed off site. A <10kg handheld breaker arranged for site work. |
5 Jan 2026 |
|
29 Dec 2025 |
At Viaduct 1, opened cement bags without properly covered by impervious materials was found. |
Dusty material with improper storage removed from working area. |
5 Jan 2026 |
|
29 Dec 2025 |
At Viaduct 3, appropriate dust suppression measures should be implemented for temporary Stockpile. |
Cement slurry covering was provided to the stockpile. The implementation of such measures will be kept in view, and the Contactor will control the height of stockpile and arrange for on-site backfill at earliest. |
5 Jan 2026 |
|
5 Jan 2026 |
At TCCS, general refuse was scattered on the ground. |
At TCCS, the contractor cleaned up the site. |
12 Jan 2026 |
|
5 Jan 2026 |
At TCCS, the breaker tip was found on bare ground without spillage prevention measures. |
At TCCS, protective measure was provided underneath the breaker tip. |
12 Jan 2026 |
|
5 Jan 2026 |
At Viaduct 1, gully of public drainage was found unprotected. |
At Viaduct 1, geotextile was placed at the gully. |
12 Jan 2026 |
|
5 Jan 2026 |
At Viaduct 1, chemical containers were found without drip tray. |
At Viaduct 1, chemical containers were removed. |
12 Jan 2026 |
|
5 Jan 2026 |
At newly established site area of Viaduct 1, no EP was presented at site entrance. |
At newly established site area of Viaduct 1, EP was presented at site entrance. |
12 Jan 2026 |
|
5 Jan 2026 |
At Viaduct 1, minor site runoff was observed leaking to public access. |
At Viaduct 1, bunding was provided to the drilling rig to prevent runoff. |
12 Jan 2026 |
|
12 Jan 2026 |
At TCCS, the grouting works was conducted. The Contractor should cover the grouting works with impervious material on top and 3 sides to prevent potential dust nuisance and comply with APCO requirement. |
Grouting stopped immediately. Improper equipment and material were removed from the site. |
23 Jan 2026 |
|
12 Jan 2026 |
At Viaduct 1, the drainage was accumulated with sand. |
The surface channel has been cleaned up, sand bags were placed for protection. |
23 Jan 2026 |
|
12 Jan 2026 |
At Viaduct 1, the contractor should cover the cement bags with impervious material to prevent dust nuisance. |
Dusty material was covered by impervious sheet immediately, all material removed from working area. |
23 Jan 2026 |
|
12 Jan 2026 |
At Viaduct 1, accumulated stagnant water was found in the drip tray. |
At Viaduct 1, stagnant water removed and drip tray is cleared. |
23 Jan 2026 |
|
12 Jan 2026 |
At Viaduct 1, the drilling rig NRMM label was damaged. |
At Viaduct 1, NRMM label of the drilling rig was replaced. |
23 Jan 2026 |
|
12 Jan 2026 |
At KLWR, the contractor should adopt dust suppression measures for the stockpile. |
At KLWR, the stockpile was covered by impervious sheet. |
23 Jan 2026 |
|
23 Jan 2026 |
At KLWR, appropriate dust suppression measures should be implemented for unpaved surface. |
At KLWR, dust suppression measure was provided. |
27 Jan 2026 |
|
23 Jan 2026 |
At Viaduct 1, dusty surface was observed. |
At Viaduct 1, the dusty surface was cleaned up. |
27 Jan 2026 |
|
23 Jan 2026 |
At Viaduct 3, generator with exempted NRMM label was observed. |
At Viaduct 3, generator with exempted NRMM label was removed from site. |
27 Jan 2026 |
|
27 Jan 2026 |
At TCCS, the contractor was reminded to display the EP at the site entrance. |
On-going |
-- |
|
27 Jan 2026 |
At Viaduct 1, NRMM label was not found on the excavator. |
On-going |
-- |
|
27 Jan 2026 |
At KLWR, some of the concrete slurry overflowed. |
On-going |
-- |
|
27 Jan 2026 |
At KLWR, mud track was observed at the site exit. |
On-going |
-- |
In accordance with Condition 2.16 of the EP,
all dump trucks for construction and demolition (C&D) materials
transportation and disposal shall be equipped with Global Positioning System
(GPS) or equivalent automatic identification system (AIS) for real time
tracking and monitoring of their travel routings and parking locations in order
to avoid illegal dumping or landfilling of C&D materials. The data
collected by GPS or equivalent AIS relating to travel routings and parking
locations of all dump trucks shall be recorded properly for checking and
auditing by ET and IEC respectively. Checking and auditing on the travel
routings and parking locations collected by GPS was done in the reporting
period. No illegal dumping or landfilling of C&D material was found in the
reporting period.
The monthly
summary of the waste flow table is provided in Appendix G.
The valid environmental permits and licences
for the ATCL during the reporting period are summarised in Table
5.2.
Table 5.2: Valid Environmental Permits / Licences
|
Type of Permit / Licence |
Reference No. |
Valid From |
Valid Till |
Remark |
|
Environmental Permit |
EP-630/2023/A |
1 Dec 2025 |
-- |
N/A |
|
Billing Account for Disposal of Construction Waste |
7055562 |
12 Aug 2025 |
-- |
N/A |
|
Construction Dust Notification under APCO |
10020078 |
4 Aug 2025 |
-- |
N/A |
|
Construction Noise Permit |
GW-RS0069-26 |
25 Jan 2026 |
28 Feb 2026 |
Issued by EPD on 23 Jan 2026 |
|
Chemical Waste Producer |
5213-951-P3620-01 |
25 Aug 2025 |
-- |
N/A |
|
Water Discharge Licence |
-- |
-- |
-- |
Under Application |
Air
Quality
There was no exceedance of the Action or Limit
Levels for impact air quality monitoring during the reporting period.
Noise
There was no exceedance of the Action or Limit
Levels for impact construction noise monitoring during the reporting period.
Water
Quality
No impact
water quality monitoring was conducted during the reporting period.
Statistics on exceedance of the Action or Limit
Levels for environmental monitoring are summarized in Table
6.1.
Table 6.1: Statistics on Exceedance of the Action or
Limit Levels for Environmental Monitoring
|
Environmental Monitoring |
No. of Exceedances Recorded during the Reporting Period |
Cumulative No. of Exceedances Recorded since the Project Commenced |
|||
|
Project related |
Non-project related |
Project related |
Non-project related |
||
|
Air Quality |
Action Level |
0 |
0 |
0 |
0 |
|
Limit Level |
0 |
0 |
0 |
0 |
|
|
Construction Noise |
Action Level |
0 |
0 |
0 |
0 |
|
Limit Level |
0 |
0 |
0 |
0 |
|
|
Water Quality |
Action Level |
-- |
-- |
-- |
-- |
|
Limit Level |
-- |
-- |
-- |
-- |
|
Complaint Log
There was no complaint received in
relation to the environmental impact during the reporting period.
Notifications of Summons or Status of
Prosecution
There was no notification of summons
or prosecutions received during the reporting period.
Cumulative Statistics
Statistics on complaints, notifications of
summons and successful prosecutions are summarized in Table
6.2.
Table 6.2: Statistics on Environmental Complaints,
Notifications of Summons and Successful Prosecutions
|
Reporting Period |
Environmental Complaints |
Notifications of Summons |
Successful Prosecutions |
|
This reporting period (1 - 31 Jan 2026) |
0 |
0 |
0 |
|
From commencement date of construction to end of reporting period |
0 |
0 |
0 |
The implementation status of
environmental protection and pollution control/mitigation measures during the
reporting period is presented in Appendix H.
As informed by the Contractor, the major
construction activities for the next reporting period are summarized below:
Land-based
portion
·
Pre-drilling
(site preparation works);
·
Site
clearance (site preparation works); and
·
Piling
works.
Marine-based
portion
·
Pre-drilling
(site preparation works).
The tentative schedule for weekly site
inspection and environmental monitoring for the next reporting period is
provided in Appendix F.
General
The construction works for the Project
commenced on 17 December 2025; therefore, the construction phase EM&A
programme of the ATCL Project started on 17 December 2025. During the reporting
period, no marine works in relation to the marine viaduct was undertaken thus
no water quality monitoring was conducted. The ET of the Project has undertaken
environmental site inspections and environmental monitoring under the
construction phase EM&A programme during the reporting period.
Environmental Monitoring
Air quality and noise monitoring was conducted
during the reporting period, and no exceedance of Action and Limit Levels was
recorded.
Environmental Site Inspections
Weekly environmental site inspections were
conducted during the reporting period. No major deficiency was identified
during the site inspections. Nevertheless, recommendations on good practices
and mitigation measures were given to the Contractor during the site
inspections.
Complaint Log
There was no complaint received in relation to
the environmental impact during the reporting period.
Notifications of Summons and
Successful Prosecutions
There was no notification of summons
or successful prosecutions received during the reporting period.
Reporting Changes
There was no reporting change during the
reporting period.
Recommendations on Compliance / Mitigation
Measures Implementation
According to the environmental site inspections
conducted during the reporting period, the following recommendations were
provided:
Air Quality
·
Regular
watering should be adopted to reduce dust emissions from all exposed site
surfaces with unpaved roads.
·
Open
stockpiles shall be avoided or covered.
·
Bags
of cement should be covered entirely by impervious sheeting.
·
Handling
of bulk cement should be carried out in a totally enclosed system or facility,
and any vent or exhaust should be fitted with an effective fabric filter or
equivalent air pollution control system.
·
Avoid
usage of exempted NRMMs as far as practicable.
·
Requirements
stipulated in the Air Pollution Control (Non-road Mobile Machinery) (Emission)
Regulation should be followed to control potential emissions from non-road
mobile machinery.
Water Quality
·
Channels,
earth bunds or sand bag barriers should be provided on site to direct
stormwater to silt removal facilities.
·
Manholes
(including newly constructed ones) should always be adequately covered.
·
All
vehicles and plant should be cleaned before leaving a construction site. An
adequately designed and sited wheel washing facilities should be provided.
Waste Management
·
Remove
waste in timely manner.
·
Drip
tray should be provided to chemical waste containers. The drip tray should be
clean up regularly.
Others
·
A
copy of the valid Environmental Permit shall be displayed conspicuously on the
Project site(s) at all vehicular site entrances/exits or at a convenient
location for public’s information at all times.